Multi-stop route

A vehicle route with several jobs in sequence. Each stop's arrival depends on every stop before it, which is why delays and wide windows build through the day.

See the problem. Try the solution.

The lead is ready. The calendar looks open.

A homeowner asks for 10:00. The technician finishes the previous job at 10:00 across town.

HOMEOWNER ON THE PHONE“Can you come at 10?”
One technician’s morningTuesday
Previous appointmentFinish the work already booked.
30 min travelAt this time of day
New service appointment60 minutes on site
Next appointment · 20 min away
10:00Open on the calendar.
Still on the road.
Travel fits.
The work fits.
10:30 fits this sample day.
01 / 04Skip to details

A multi-stop route is a single vehicle's sequence of several job sites in one day, where the truck drives from one stop to the next instead of returning to the shop between jobs.

How a multi-stop route is measured

Each stop's arrival time is built from everything before it.

Arrival at stop n = Start time + Sum of on-site times for stops 1 to n−1 + Sum of drives for legs 1 to n

Drive per stop = Total drive time ÷ Number of stops

Say a truck starts at 8:00. Stop 1 is 20 minutes away and takes 60 minutes. Stop 2 is 30 minutes further and takes 90. The leg to stop 3 is 25 minutes. Arrival at stop 3 is 8:00 + 20 + 60 + 30 + 90 + 25 = 11:45. If stop 1 runs 30 minutes long, stop 3 becomes 12:15, and so does every later stop unless something absorbs it.

Why it matters

That chain is why the last arrival window of the day is usually the widest. Uncertainty in job length and drive adds up stop by stop. It is also why a single bad leg is expensive: it delays every remaining stop, not just one.

Two things keep multi-stop routes reliable:

  1. Legs that were checked. Each drive should be computed from the previous stop, not from the shop. A route that assumed "15 minutes between jobs" everywhere will drift.
  2. Order that avoids backtracking. Stops should progress across the area instead of zig-zagging.

Route optimization handles the second, given a set of stops. The first is decided when each stop is booked. Travel-feasible scheduling means a stop only gets added to a route if the truck can reach it from the stop before.

CrewLink applies that check before a slot is offered, computing travel from where the truck will actually be. The result is a multi-stop route built leg by leg, visible on the dispatch board.

A common mistake

Adding a stop by looking only at the gap. A free hour between stop 3 and stop 4 looks like room for a short job. But the new job adds two legs: from stop 3 to it, and from it to stop 4. If those drives eat the hour, stop 4 is now late.

Related terms

Common questions

How many stops should a service route have?

It depends on job length and drive. Divide the working day by average job time plus average drive per stop to get a realistic number.

Why do later stops on a route run late?

Delays and drive estimates add up. Any overrun earlier in the day pushes every later stop unless the schedule has slack.

Does a multi-stop route start at the shop?

Often, but not always. Some technicians start from home. Compute the first leg from wherever the truck actually begins.

See your own day on it

CrewLink offers only the times a crew can actually reach, from where the truck will be. Try the sample day, then start free with your own trucks and services: no credit card for your first 50 scheduled jobs.